Networking Projects
Summary of Project Performance – Network Upgrades
(for the period 01-Oct-2008 through 20-April-2009)
| Project Deliverable / Milestone |
Initial Completion Target |
% Complete (0,25,50,75,100) |
Current Completion Target |
| GCC Add Core Switch |
9/2009 |
25% |
8/2009 |
| GCC, FCC,LCC Add Access Switches |
9/2009 |
25% |
9/2009 |
| Upgrade WH Access Switches |
9/2009 |
5% |
? |
| Upgrade Switch Supervisor Modules |
9/2009 |
25% |
9/2009 |
| Upgrade Switch Interface Cards |
9/2009 |
25% |
9/2009 |
| Upgrade Village Wireless Network |
9/2009 |
25% |
8/2009 |
| Upgrade VPN System and Capacity |
9/2009 |
75% |
7/2009 |
| Diagnostic Tools and Utilities |
9/2009 |
50% |
6/2009 |
| VOIP Production |
|
0% |
|
Summary of Project Performance – Network Investigations
(for the period 01-Oct-2008 through 20-April-2009)
| Project Deliverable / Milestone |
Initial Completion Target |
% Complete (0,25,50,75,100) |
Current Completion Target |
| VOIP - Pilot |
9/2009 |
90% |
5/2009 |
| IPv6 |
9/2009 |
10% |
9/2009 |
| Network Tools |
9/2009 |
100% |
11/2008 |
| Network Security |
9/2009 |
25% |
9/2009 |
- All projects completion dates are subject to change based on when equipment arrives
- “% Complete” is a coarse-grained subjective evaluation.
–0% = not started –25% = started, not much significant progress as yet –50% = significant progress –75% = significant progress and nearly complete, preparing for completion –100% = absolutely complete.
|
|